- The Walloon Region ordered Google on November 26 to stop building at its Farciennes site near Charleroi; about 300 workers were on site, an official said.
- Minister François Desquesnes revoked an amended permit in August that would have let Google draw 600 cubic metres of Sambre water per hour, but work continued.
- Google has asked the Council of State to annul the revocation and says its original air-cooled permit is still valid; a public hearing is set for January 7.
Belgium's Walloon Region has told Google to stop building its data centre in Farciennes, near Charleroi. The order came on Thursday, November 26, according to The Next Web. Raphael Stokis, a senior regional official, told the Flemish broadcaster VRT that around 300 construction workers were on site when it arrived.
A permit that no longer exists
The dispute is over water. Google received a permit in 2024 for three air-cooled data centres at the site, which spans Farciennes and Aiseau-Presles. In 2025 it changed the plan, merging two buildings into one larger one and switching to cooling with water from the Sambre river. The Walloon administration approved that amended permit in April 2026.
Residents appealed. In August, François Desquesnes, the regional minister for territory and infrastructure, revoked the amended permit. According to Belga, the request covered drawing 600 cubic metres of river water an hour, with less than a quarter returned to the Sambre. The minister pointed to pressure on Wallonia's water resources and the prospect of more frequent droughts.
Construction kept going anyway. Google says its original air-cooled permit remains valid, Techzine reports; the regional government disagrees, arguing that the work on site includes elements covered by the revoked permit. Techzine says work continued on the roof and other parts of the site. The project has been presented as an investment of about €1 billion.
Greenpeace and the courts
Greenpeace Belgium, alerted by residents, used satellite images to show that work had carried on for months, then launched an emergency procedure earlier in the week. Desquesnes announced an investigation on Wednesday, and the halt order followed. A Greenpeace spokesperson, Nadia Cornejo, said the step should have been taken in August, when the permit was cancelled.
On October 17, Google asked Belgium's Council of State to annul and suspend the minister's decision. Greenpeace and several residents applied to join the case on November 16. In a statement to VRT, a Google spokesperson said the company remains committed to an open and collaborative dialogue with the regional government and experts.
Google plans three new data centres in the province of Hainaut, according to Techzine, and already runs a large campus at Saint-Ghislain, about half an hour's drive away. The Next Web notes that its data centre project in Finland has also drawn a police investigation. The Council of State's public hearing is scheduled for January 7.